Factory Calendar Settings in APO?



How to change Factory Calendar Settings in APO?
We have some wrong Public Holidays in Factory Calendar in APO & not same like R/3.
How can we change these settings in APO?
I know program RSIMPCUST in APO can import all Global settings for Factory Calendar from R/3 to APO, but it don not update the changes, but Rebulit it ( means deletes all entries & reload again). Is it ok if we Rebuilt the data, will it not affect any Transactional data which is there in APO system right now?
Request you to help.              


Hi,
There is no impact if you rebuilt the FC and this is the only way we have to follow.
Always you have to sinc it from ECC.             